Construction Feasibility and Cost Study Deliverables
By Anadolu Mimarlık

An affordable fit-out estimate can sit inside a project that is unsuitable because of its use, access or tenure. Feasibility examines those wider constraints before the client commits to a defined construction scope.
The decision behind the commission
Put the client’s question at the start of the brief. It might concern an acquisition, an extension or a choice between refurbishment and replacement. Give the consultant the business requirement, site information, budget basis and decision date. That allows the team to choose the necessary investigations and explain which conclusions it can reasonably reach within the commission.
Agree the study boundary. Does it include measured information, structural advice, services assessment, planning advice, cost planning or a commercial appraisal? Identify work undertaken by other specialists and information supplied by the client. A consultant can coordinate an assessment without personally designing or certifying every discipline.

Separate facts, assumptions and investigations
Require a register of information used, its date and limitations. Existing drawings, lease extracts, condition reports and utility records can each contain gaps. Mark what has been checked on site and what remains unverified. The report should explain which uncertainty is material to the decision and how it can be reduced.
For a potential office acquisition, for example, the available layout may suggest that the space fits the planned team. Feasibility still needs to examine whether services, access, tenure and permissions support that use. If capacity information is unavailable, the report should recommend a defined investigation and show the consequence of a negative result.
Options worth comparing
Develop a manageable set of alternatives against the same requirements. Include a limited-intervention option where credible and explain why an option has been rejected. Record capital scope, operational effect, disruption, maintenance, programme and risk. Avoid ranking options only by the lowest initial construction price.
| Decision heading | Useful report output |
|---|---|
| Function | Which requirements each option meets or compromises |
| Technical feasibility | Evidence, specialist conclusions and unresolved tests |
| Cost | Estimate basis, included packages, exclusions and uncertainty |
| Programme | Dependencies, decision dates and lead-time assumptions |
| Risk | Potential consequence, owner and next action |
Request a cost plan that can be updated
Use a consistent structure so that the estimate can develop as design information improves. RICS's NRM suite provides measurement and cost-management guidance, including early cost estimating and capital-works cost planning. Ask which area basis, quantities and rates have been used and which items are allowances. Keep professional fees, taxes and operational costs identifiable.
Show uncertainty beside the affected package. If ground conditions are unknown, distinguish the base assumption from the cost and programme consequence of a different finding. A single contingency number without an explanation can hide the very issue the client needs to investigate before purchasing or commissioning further work.
Use value engineering to preserve required performance
Value engineering starts with the function that must be retained. Agree which requirements are fixed and where alternatives are possible, then compare installation and operation over time. Maintenance access, replacement and interruptions to use belong alongside the purchase price.
For instance, a cheaper ceiling system may require frequent access closures for maintenance, while an alternative allows local panel replacement. The decision needs an operator's input and realistic care assumptions. Record the chosen option and its conditions so a later tender substitution does not quietly undo the assessment.
End with a decision and next-stage brief
The final report should name the recommended option, the evidence supporting it, material qualifications and the next commitment. Identify surveys, specialist appointments, applications and design outputs needed next, with responsibility and sequence. If the evidence is insufficient to decide, say exactly what is missing and what investigation will resolve it.
Keep the study as the baseline for later scope and cost reviews. When the brief changes, record which assumptions and conclusions must be reconsidered.
Frequently asked questions
- Is feasibility the same as detailed design?
- No. Feasibility tests options and establishes whether and how to proceed. Detailed design develops the chosen solution into coordinated information appropriate to the next procurement or construction stage.
- Should a feasibility estimate be treated as a fixed price?
- No. Its reliability depends on the information, scope, quantities and assumptions available. Ask for the estimate basis, exclusions and risks before using it to make a commitment.
- What if the consultant cannot recommend one option?
- The report should identify the missing evidence and the investigation or decision needed. A qualified recommendation can be useful; an unexplained preference or unsupported certainty is not.